Authority: National Company Law Tribunal, Court Room No. 1, Mumbai Bench, Single Bench
Order Date: 18.06.2026
Case Overview
The order pertains to Appeal No. 238 of 2026 filed by Trocko Logi Private Limited under Section 10 and Rule 63 of the National Company Law Tribunal Rules, 2016. The appeal was filed with a delay. The appellant's legal representatives, Adv. Avinash R Khanolkar along with Adv. Mahesh Nulolu and Adv. Shivani Prabhukhanolkar, were present at the hearing. The bench noted that there was no satisfactory explanation provided for condoning the delay in filing the appeal.
Final Outcome
In the interest of justice, the Hon'ble Member (Judicial), Sh. Sushil Mahadeorao Kochey, allowed the appeal and condoned the delay subject to specific conditions. A cost of Rs. 10,000/- was imposed, to be paid by the appellant from his own pocket to the Prime Minister's National Relief Fund using the Virtual Payment Address pmnrf@centralbank. The appellant is required to file proof of this payment with the Registry. Upon verification of the payment proof, the Registry is to allow the appellant to cure the defects in the appeal. The appellant is granted seven days, calculated from the date the order is uploaded on the portal, to remove all defects and upload a defect-free copy on the DMS Portal. This is stated to be a last opportunity. The order explicitly states that failure to comply with any of these conditions will nullify the effect of this order and the appeal shall stand dismissed automatically. With these observations and directions, Appeal No. 238 of 2026 was allowed and disposed of.
Topics: NCLT Proceeding, Corporate Legal Compliance