Authority: Supreme Court of India

Order Date: 28-11-2026

Case Overview

  • Petitioner: Uniworth Ltd
  • Respondents: State of Chhattisgarh & Others
  • Special Leave Petition (Civil) Diary No. 24170/2019, arising from the impugned final judgment and order dated 28-11-2018 in WPC No. 1598/2016 of the High Court of Chhattisgarh, Bilaspur.
  • Multiple interim applications were filed (IA No. 119072/2019, IA No. 119074/2019, IA No. 119073/2019, IA No. 121130/2019, IA No. 121128/2019) seeking condonation of delay, exemption from filing certain documents, and permission to file additional annexures.
  • Counsel for petitioner: Mr. Vanshdeep Dalmia, Ms. Anisha Jain, Ms. Shambhavi Singh.
  • Counsel for respondents: Mr. Atul Jha (A.A.G.), Mr. Abhishek Pandey (Standing Counsel), Mr. Prashant Kumar Umrao, Mr. Prashant Singh.
  • The Court examined the impugned judgment and Section 3 read with Section 2(d‑i) of the Chhattisgarh Electricity Duty Act, 1949.
  • Petitioner argued that Section 3 does not apply because it is not a "producer" within the meaning of Section 2(d‑i).

Observations & Reasoning

  • The Court questioned why the petitioner challenged Section 3 if it does not fall within its definition of "producer".
  • It found the High Court’s dismissal of the original writ petition justified.
  • The Court concluded that the Special Leave Petition lacks merit.

Directions

1. Delay in filing is condoned.

2. The Special Leave Petition is dismissed.

3. The petitioner may respond to any demand notices; such a response will be considered, and a speaking order will be passed thereafter.

4. Any pending applications, if any, are to be disposed of.

Final Outcome

  • The Supreme Court dismissed the Special Leave Petition, affirming the High Court’s earlier dismissal, and ordered disposal of pending applications while allowing the petitioner to reply to demand notices.

Topics: Electricity Duty, Supreme Court Decision, Taxation