Authority: High Court of Meghalaya at Shillong

Order Date: 28.10.2026

Case Overview

  • Petitioner: M/s. Varindera Constructions Limited (through Vice President, Contracts).
  • Respondent: Shri Anil Kumar Vij, IDSE, Chief Engineer (AF), Shillong Zone.
  • The dispute concerned a bank guarantee furnished by the petitioner; arbitration proceedings were conducted and an arbitral award was rendered.
  • The court observed that the arbitral award resolved the substantive issues, leaving no further matters for consideration.

Final Outcome

  • The court ordered that the bank guarantee be discharged and released within two weeks.
  • The matter was declared closed and disposed of.