Authority: National Company Law Appellate Tribunal, Principal Bench, New Delhi

Order Date: 27th July, 2026

Case Overview

This interlocutory application (IA No.5156/2026) was filed by Anisha Satish Sahitya, Proprietor of VH Roofing Solutions, against CCTEB India Pvt. Ltd. (represented by its Director, Guobing Jiang). The appellant sought an extension of time for curing defects in a memo of appeal that was initially e-filed on 26th May 2026. The NCLAT registry scrutinized the appeal and intimated defects to the appellant on 4th June 2026. The appellant refiled the appeal on 22nd July 2026, citing a delay caused by the requirement for the appellant's physical signature while she was located in Hyderabad, while the appeal was being processed in Delhi. Subsequent defects raised by the registry after the first refiling caused further delays, resulting in a total delay of 41 days beyond the stipulated 7-day period for curing defects.

Final Outcome

The Registrar, after hearing the appellant's counsel and perusing the application and office report, noted the 41-day delay in refiling the memo of appeal. The case was directed to be placed before the Hon'ble Bench for appropriate orders under the heading 'for admission with defect (fresh case)'.

Topics: NCLAT Procedure, Appeal Defects, Time Extension