Background Context

This disclosure is in continuation of the company's earlier intimation dated 14-01-2026 regarding termination notice from North Western Railway for the contract involving "Earthwork in filling/cutting in formation, Blanketing, construction of station building including electrical and S&T structures, Passengers/ goods platforms, Platform shelters, Foot over bridges, Passenger amenities work, S&T structures, staff quarters, LHS /RUBs, Minor Bridges, Retaining walls, Toe wall, pitching work and all other ancillary works between Jaipur- Chaksu stations from Km 131.270 to Km 87.60 in connection with Jaipur- Sawai Madhopur Doubling Project".

Court Judgment Details

  • Case Reference: SB Civil Writ Petition No. 983/2026 connected with SBCWP 8878/2026
  • Court: High Court of Judicature for Rajasthan, Jodhpur
  • Judgment Reserved: 21-07-2026
  • Judgment Pronounced: 17-08-2026
  • Detailed Judgment Received: 19-08-2026

Court Order Contents

  • The Company is directed to avail alternative efficacious remedy before the competent forum
  • Status quo (as on the date judgment was reserved) shall be maintained for a period of 45 days from the date of pronouncement (17-08-2026)

Financial Implications

  • Performance Guarantee and Security Deposit were already encashed prior to this judgment
  • No further financial implication as of now
  • Fresh NIT of Department cannot be decided now as no Letter of Award (LOA) was issued up to 21-07-2026

Company Action

The Company has decided to avail appropriate and efficacious remedy by filing petition before competent forum as directed by the Hon'ble Court.

Additional Information