Authority: High Court of West Bengal
Order Date: 23 November 2026
Case Overview
- Petitioners: Madhusudhan Karmakar and another; Respondents: State of West Bengal, West Bengal State Electricity Distribution Company Limited (WBSEDCL), Rajpur Sonarpur Municipality, and a private club (respondent no.10).
- Dispute: An electric post was installed on a plot of land that is subject to a pending civil suit (T.S. No. 109 of 2005) and an injunction dated 9 March 2006 directing parties to maintain the status quo.
- The injunction remains subsisting. The municipality installed the post as part of a State Government scheme, with the District Magistrate as the executing authority.
- WBSEDCL affirmed it had earlier provided a connection to the private club but did not install the post nor supply electricity to it; electricity is supplied from the municipality’s dedicated street phase.
Final Outcome
- The court directed the Rajpur Sonarpur Municipality (respondent no.2) to relocate the electric post outside the disputed land within twelve weeks from the date of communication of the order.
- Petitioners and the private club are to assist the municipality in re‑locating the post so that the purpose of the scheme is not disturbed.
- The writ petition (WPA 28273 of 2025) is disposed of with no order as to costs.
- Urgent photostat copies of the order may be issued upon compliance with requisite formalities.
Topics: Electric Infrastructure, Land Dispute