Authority: District Court, Samar (D/L Sl-14 Ct. 07)
Order Date: 17.07.26
Case Overview
- Petition: Mosharof Hossain v. WBSEDCL & Ors., WPA 15439 of 2026.
- Petitioner's counsel: Anindya Bose, G. Mahiuddin, Raina Das, Kaif Hossain.
- Respondent's counsel: Soumyajit Chakraborty for WBSEDCL.
- Issue: Petitioner's request for electricity supply to his submersible pump.
- WBSEDCL conducted two inspections of the pump installation.
- WBSEDCL indicated that, if the installation is found satisfactory, a quotation would be issued within a week.
- No quotation had been issued at the time of the hearing.
Final Outcome
- The Court disposes of the writ petition, directing WBSEDCL to effect electricity supply to the petitioner’s submersible pump, provided the petitioner is eligible and legally entitled.
- The petitioner must complete all requisite formalities and pay the applicable charges within four weeks from the date of compliance with those formalities.
- No order as to costs was made.
- An urgent certified copy of the order may be supplied to the parties upon compliance with all requisite formalities.
Topics: Electricity Supply, Court Order