Authority: Supreme Court of India

Order Date: 05-08-2026

Case Overview

  • Petitioners: West Bengal State Electricity Transmission Company Limited & others; Respondents: Somnath Mukherjee & others.
  • Special Leave Petition (Civil) No.11842/2025 arising from the impugned final judgment and order dated 20-09-2024 in RVW No.153/2024 and MAT No.1136/2023 passed by the Calcutta High Court.
  • The petition seeks condonation of delay in filing IA No.76552/2025 and exemption from filing a certified copy of the impugned judgment (IA No.76553/2025).
  • Hearing held on 04-08-2026 before Hon’ble Justices Ahsanuddin Amanullah and Manmohan. Counsel for petitioners and respondents listed.

Final Outcome

  • The Court, considering a letter dated 31-08-2026, granted the respondents’ prayer.
  • An interim order was issued to continue the proceedings until the next date of listing, which is scheduled for 31-08-2026.
  • The order was digitally signed by Pooja Sharma on 05-08-2026.

Topics: Legal Proceedings, Power Utilities