Background

In July, Bengaluru Development Minister Krishna Byre Gowda inspected a freshly asphalted service road on the Outer Ring Road and found it had been excavated again. Officials could not identify the responsible agency; BESCOM denied involvement and an optical‑fibre cable company was mentioned as a possible culprit. The incident highlighted a systemic problem where one agency constructs a road and another later digs it up without a unified record of the work.

Existing Road‑History System

Bengaluru had already established a road‑history initiative more than ten years ago. The system, built on the GeoCivic platform, mapped approximately 13,000 kilometres of roads and assigned a unique identification number to each road stretch, irrespective of street‑name variations. Each ID linked to the location, road length, work orders, contractor name, sanctioned amount, completion details and the defect‑liability period during which the contractor remains responsible for rectifying defects. The programme was recognised with the 2014 WeGO Best e‑Government Prize (Efficiency category) for its GIS‑enabled implementation, the first such award for an Indian urban local body, and was executed under Mr G Manjunath Raju.

Ministerial Directives

In September, the minister directed officials to introduce digital, time‑bound contractor‑bill processing that is tied to actual work progress. He also called for a common GIS‑based platform to map roads, underground utilities and planned civic works, aiming to ensure that no road work proceeds without a valid road ID and that every excavation, restoration or utility intervention is recorded against that ID.

Challenges with Duplicate Work and Utility Mapping

The release cites the risk of duplicate tenders: a road that has already been white‑topped may receive a second tender for the same physical stretch under a different street name, allowing duplicate claims to escape detection. The local phrase "hale kallu, hosa bill" (old stone – new bill) illustrates this problem. A mandatory road ID would enable officials to verify previous sanctions, completed works and payments before approving new tenders, making duplication harder to conceal.

Underground utilities—managed by BWSSB, BESCOM, gas companies and telecom providers—are often recorded separately, leading to outdated maps as highlighted by the CAG. Inaccurate utility data increases the risk of damaged pipes and cables, repeated excavations and avoidable expenditure. The minister’s proposal requires each utility agency to map its infrastructure against the common road IDs, recording location, depth and updating the data whenever work is undertaken. Every road‑cutting permission must be linked to the relevant ID, with restoration verified through geotagged photographs and inspection.

Recommendations and Implementation Path

Three essential changes are outlined:

1. No road work should be tendered or paid for without a valid road ID.

2. All excavations, restorations and utility interventions must be recorded against the corresponding ID.

3. Public access should be provided so citizens can search by road name or number and view the work history, contractor details, expenditure, guarantee period and cutting permissions.

New roads must receive IDs at the planning stage; existing records need updating, and gaps in the database must be identified and closed. Rather than building a new standalone platform, Bengaluru should integrate its existing systems, enforce their use and open the consolidated records to the public, ensuring transparency of public‑asset spending.