Durgapur Projects Ltd Ordered 6% Interest
Retired employee Sambhu Nath Das petitioned the court seeking interest on delayed gratuity and leave encashment payments from Durgapur Projects Ltd.
Court directed DPL to calculate and pay interest at
YOUDHISTHIR DAS Granted 6% Gratuity Interest
Petitioner YOUDHISTHIR DAS retired 31 Jan 2020 from Durgapur Projects Ltd and claimed delayed gratuity under ROPA.
Court found ROPA effective from 30 Oct 2020 and ordered DPL to pay interest at 6% per
Kalipada Mal Granted 6% Interest on Retiral Dues
The High Court recognized that Kalipada Mal’s retirement dues were released late, violating the right to immediate payment.
The court ordered Durgapur Projects Ltd to pay interest at 6% per annum on t