Haryana Land Acquisition Declared Lapsed, Refund Ordered
Petitioners challenged acquisition of 26 kanal 17 marla land in Sultanpur, Sonepat, claiming lapse under Section 24(2) of RFCTLARR Act 2013.
Court found petitioners' allegations admitted, held that Se
HC Declares Haryana Land Acquisition Lapsed
The Punjab & Haryana High Court allowed the writ, declaring the 27‑01‑2006 land acquisition lapsed under Section 24(2) of the 2013 Act.
The court observed compensation was neither paid nor deposited w
Supreme Court Orders Arbitration for Kirloskar Dispute
Supreme Court allowed IA No.23115/2022, impleaded Vahine Engineering as Respondent No.28 and granted leave.
Court upheld High Court's referral of the Kirloskar family settlement dispute to arbitration