Tag
M/s Neogi Construction & Co.
2 articles
Neogi Construction Allowed Re‑submission of Solvency Certificate
Court set aside disqualification of Neogi Construction in e‑tender, citing lack of date on bank solvency certificate.
Under Clause 19.2, the committee must allow the bidder to submit a dated certifica
Neogi Construction Allowed Solvency Certificate Extension
Court set deadline of 12 November 2026 for Neogi Construction to submit dated bank solvency certificate after disqualification.
The order follows precedent set in WPA 31703 of 2026, which will govern