Project Details

  • Entity: ACME Sigma Urja Private Limited (wholly owned subsidiary of ACME Solar Holdings Limited)
  • Project Type: Battery Energy Storage System (BESS) component
  • Capacity Commissioned: 17.91 MW / 74.323 MWh (Discharge Capacity)
  • Project Location: Village Neemri, Tehsil Rawatbhata, District Chittorgarh, Rajasthan
  • Commissioning Date: October 23, 2026
  • Commercial Operation Date (COD): October 25, 2026

Project Context

This commissioning is part of a larger FDRE Project with total capacity of 250 MW / 1069 MWh (Discharge Capacity). The filing is a continuation of previous intimation dated September 30, 2026.

Cumulative Impact

With this commissioning, ACME Sigma Urja Private Limited has achieved cumulative commissioned BESS capacity of 71.640 MW / 297.292 MWh (Discharge capacity).