Project Details

ACME Solar Holdings Limited (ASHL), through its wholly owned subsidiary ACME Suryodaya Private Limited, has commissioned a Battery Energy Storage System (BESS) project with a capacity of 240.720 MWh. The project is located at Village: Sanwara and Mehar Nagar, Tehsil-Pokhran, Dist: Jaisalmer, Rajasthan.

Key Dates

  • Commissioning Date: June 30, 2026
  • Commercial Operation Date (COD): July 02, 2026

Capacity Update

With this commissioning, ACME Suryodaya Private Limited has achieved a total commissioned capacity of 285 MW / 842.624 MWh.