Project Details and Commissioning Update

ACME Solar Holdings Limited (ASHL), through its wholly owned subsidiary ACME Surya Power Private Limited, has commissioned additional capacity of its Battery Energy Storage System (BESS) project. The additional capacity commissioned is 34.598 MW / 155.493 MWh. The project is located at Village: Jaimalsar, Dist: Bikaner, State: Rajasthan. The commissioning date for this additional capacity is May 27, 2026.

Commercial Operation Date

The Commercial Operation Date (COD) for the newly commissioned 34.598 MW / 155.493 MWh capacity is set for May 29, 2026.

Cumulative Capacity Achievement

With this additional commissioning, ACME Surya Power Private Limited has achieved a cumulative commissioned capacity of 245.536 MW / 1103.392 MWh.