Date: July 01, 2026

Operational Update

Adani Green Energy Limited has commercially operationalized new renewable energy projects through its stepdown subsidiaries:

  • 156 MW wind power projects at Khavda, Gujarat (developed by Adani Green Energy Twenty Six A Limited)
  • 185 MWh Battery Energy Storage System (BESS) projects at Khavda, Gujarat (developed by Adani Renewable Energy Forty Three Limited)

Capacity Update

With the commissioning of these projects, the company has achieved:

  • Total operational renewable generation capacity: 20,141.80 MW
  • Total operational BESS capacity: 3,551 MWh

Project Details

The decision to commercially operationalize these plants was made at 10:15 PM on June 30, 2026, based on relevant clearances.

Annexure Details

Annexure A - Renewable Energy Projects:

  • Adani Green Energy Twenty Six A Limited: Wind project with 156 MW capacity

Annexure B - BESS Projects:

  • Adani Renewable Energy Forty Three Limited: BESS project with 185 MWh capacity