Key Quantitative Figures
- Proposed plant capacity: 20 TPD (Tons Per Day) CBG Plant
- Plant location: Village Maucha, Taluka Prantij, District Sabarkantha, Gujarat
Parties Involved
- Avenique Limited (CBG Producer)
- Sabarmati Gas Limited (SGL) - A Joint Venture of GSPC & BPCL (Gas Procurement)
- GAIL (Future tripartite agreement party)
Purpose/Rationale
Strengthening company's presence in renewable energy and clean fuel sector through CBG supply arrangement.
Key Conditions from Letter of Intent
- CBG must be automotive grade, compressed at 250 bar in cascade meeting IS-16087 specifications
- Biogas injection into MDPE/Steel pipeline at mutually agreed pressure meeting PNGRB specifications
- Composition requirements: CO2, sulphur and moisture under 2%; methane levels minimum 95%
- Plant must have dedicated laboratory with gas chromatograph for batch certification
- Delivery point to SGL to be communicated later
- CBG/Biogas must be odorized and free from liquids and particulate matter
- Quality monitoring system required for SGL's SCADA real-time monitoring
- Of take commences only after execution of Tripartite Agreement between GAIL, SGL and Avenique
- SGL has unrestricted access for plant inspection
- Exclusive supply to SGL without written consent prohibited
- Project milestone updates required; prior written consent needed for ownership/structure changes
- LOI acceptance required within three days of issue
- Procurement on "Reasonable Endeavour Basis" based on supply-demand scenario
- Long-term procurement price governed by Government policy
- Producer responsible for all statutory approvals
Legal Status and Next Steps
- LOI is legally non-binding and does not constitute a contract
- Does not represent SGL's opinion on credit worthiness for financial lending
- Separate definitive tripartite agreement under Synchronization scheme required
- Agreement to capture commercial terms and other conditions as agreed by parties
Financial Impact
Financial impact not quantified in the disclosure. Procurement terms and pricing will be determined by future tripartite agreement and government policy.