GAIL Revises Pipeline Completion Schedule to March 2027
GAIL's Board approved revision of completion schedule for Jagdishpur-Haldia-Bokaro-Dhamra pipeline sections to March 2027.
Delay attributed to unavailability of hindrance-free fronts for both Durgapur
GAIL Board Approves Kochi-Koottanad Pipeline Extension
GAIL's Board approved an extension for the Kochi-Koottanad-Bengaluru-Mangalore pipeline project completion to March 2027.
The project has 947 km of pipeline completed and 715 km commissioned, with a r