Date: 30.10.2026

Board Meeting Outcomes

  • The Board of Directors approved the revision in completion schedule for pipeline project sections during meeting held on 30.10.2026 (commenced at 11:00 AM, concluded at 02:25 PM)
  • Approval for extension in completion schedule is being taken up with Petroleum and Natural Gas Regulatory Board (PNGRB)

Project Details

Jagdishpur – Haldia – Bokaro – Dhamra Pipeline

  • Length Authorized/under execution (Revised Length): 3306 Km/3345 Km
  • Pipeline Completed: 3280 Km
  • Pipeline Commissioned: 3119 Km
  • Revised Completion Schedule: March 2027
  • Additional Investment Required: Not Required
  • Rationale for Delay: Delay in availability of hindrance free fronts

Dhamra – Haldia Pipeline

  • Length Authorized/under execution (Revised Length): 240 Km/253 Km
  • Pipeline Completed: 244 Km
  • Pipeline Commissioned: 150 Km
  • Revised Completion Schedule: March 2027
  • Additional Investment Required: Not Required
  • Rationale for Delay: Delay in availability of hindrance free fronts

Distribution

Copy sent to:

  • Deutsche Bank AG, Filiale Mumbai - TSS & Global Equity Services, The Capital, 14th Floor C-70, G Block, Bandra Kurla Complex, Mumbai - 400051
  • Beacon Trusteeship Limited - 4C and D Siddhivinayak Chambers, Gandhi Nagar, Opposite MIG Cricket club, Bandra East, Mumbai - 400051