GAIL (India) Limited has made a regulatory disclosure under Regulation 30 of SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015, regarding the extension of completion schedule for the Kochi-Koottanad-Bengaluru-Mangalore Pipeline (KKBMPL) Project.

The disclosure provides detailed status of the pipeline project:

  • Project Name: Kochi-Koottanad-Bengaluru-Mangalore Pipeline (KKBMPL) Project
  • Length Authorized/Under Execution (Revised Length): 1104 Km / 951 Km
  • Pipeline Completed: 947 Km
  • Pipeline Commissioned: 715 Km
  • Revised Completion Schedule: March, 2027
  • Additional Investment Required: Not Required
  • Rationale for Extension: Delay in availability of hindrance free fronts

The Board of Directors of the Company approved this extension in its meeting held on 30.10.2026, which commenced at 11:00 a.m. and concluded at 02:25 p.m.

Approval for the extension in completion schedule of the project is being taken up with the Petroleum and Natural Gas Regulatory Board (PNGRB), the sector regulator.

This disclosure is a continuation of the company's previous communication dated 13.04.2026 and is made in compliance with SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015.

The letter was signed by Deepak Asija, Company Secretary, and digitally signed on 30.10.2026 at 14:31:09 IST.