Order Details
- L&T's Renewables business vertical has won a major order to develop three Battery Energy Storage System (BESS) projects for a notable client in the Middle East
- The three projects will collectively contribute to 6 gigawatt-hour of storage capacity
- Each project features a 4-hour Battery Energy Storage System (BESS) capable of storing and dispatching energy
Project Scope
- Development of three BESS projects
- Grid interconnections including pooling substations and underground cables
- Advanced BESS solution incorporating liquid cooling technology for higher power density, enhanced safety and extended operational life
Technical Specifications
- 6 gigawatt-hour total storage capacity across three projects
- 4-hour Battery Energy Storage System for each project
- Liquid cooling technology implementation
- Capable of energy shifting - storing surplus clean energy during off-peak periods and delivering during peak demand hours
Strategic Significance
- Marks one of the most impactful advancements in grid modernization and renewable energy integration across the Middle East region
- Positions L&T as a key EPC player in the fast-growing energy storage sector
- Demonstrates client trust in L&T's engineering excellence and project management expertise
- Supports grid stability and renewable energy integration in the region
Project Challenges
- Stringent requirements with respect to plant performance
- Workforce mobilization challenges
- Safety and quality standards
- Timeline constraints
Company Background Context
Larsen & Toubro is a USD 32 billion Indian multinational engaged in EPC Projects, Hi-Tech Manufacturing, Products and Services, operating across diverse domains and multiple geographies.
Order Classification
Classified as a "Major" order according to the company's order classification system.