NTPC Board approved a 4.70 GWh Battery Energy Storage System project at an estimated cost of Rs. 5,821.90 Crore.
Additional equity of Rs. 3,173.67 Crore committed in JV firm MUNPL, raising total equity commitment to Rs. 5,000 Crore.
The MUNPL investment supports Meja Super Thermal Power Project Stage-II (3x800 MW), with completion targeted by 2029-30.